The bath and solid fuel range (Stanley Donard) were fitted on Tuesday by the plumbers.
The hole for the flue was in the wrong place in the wall - so they had knock out a new one - so theres a bit of a mess to tidy up now. It will be tiled around there - so it doesnt need to be 100% smooth.
The tiles were all delivered yesterday - and the tiler is expected on Monday.
The carpenter is due next Tuesday to start doing the floors and doors upstairs. He said he would also d the doors downstairs too - he doesn't think the moisture will affect them.
The laminate flooring came too - and the underlay. I ordered soundproof underlay for upstairs -
Painting is nearly done - the hall has had one coat and there are 2 bedrooms that need a final coat and the landing needs one more too.
No comments: