The first phase of the house build wil soon be over. The roof slates will go on next week (weather permitting) and the first floor partition walls will be put up.
We hired one builder to do the foundations, walls and roof. Once these are finished - we have to organise electician, plumber, plasterer, tiling, flooring, sewage, drains, painting, kitchen (have I forgoten anything?) So up to now it has been fairly easy going. It might get a bit more stressful during the next few weeks.
We have had a couple of Kitchen prices - nearly 80% difference in them. We are seeing another one on Monday. I am talking to an electrician on Sunday. We might have a temporary supply of electricity in soon. The man from the ESB (Elec Supply Board) was over last week checking out the best way to bring the supply to the house, There is a transformer in the next field - so they are going to run a cable underground from there.
We need to start thinking about internal doors, bathroom suites, and loads of other things soon. Should be fun.